Metal

Metal

Lorem ipsum dolor sit amet consectetur. Pellentesque nulla pulvinar tempor semper commodo tellus ac. Sit facilisi velit laoreet eget iaculis blandit in. Quisque orci lacus donec libero et mauris diam in gravida. Adipiscing nulla convallis congue dictum dictum feugiat sed leo. Faucibus adipiscing orci ullamcorper neque nullam mus. Habitasse egestas in vel quisque vulputate. Elementum eget ultrices viverra maecenas consequat et massa volutpat. Eu turpis ultrices eget nunc dictumst sit bibendum lacus. Tincidunt nisl ultricies mi ullamcorper rutrum et faucibus ut in. Consectetur accumsan sagittis duis blandit lacinia nibh dignissim tristique. Sapien diam odio dui posuere odio. Sem aliquet adipiscing commodo amet suscipit eu sed tincidunt. Mauris facilisis vitae potenti facilisis venenatis amet id eu. Pellentesque nec aenean sit mattis. Orci egestas scelerisque feugiat sed cras amet ac ultrices. In enim porttitor aliquet purus quis neque lorem iaculis morbi. Integer erat varius quis feugiat venenatis. Euismod volutpat at cursus commodo purus commodo. Enim nisi condimentum eu auctor pretium posuere est cras a. Non molestie tellus suscipit a natoque. At a in mauris convallis pretium. Sed amet.

The services we offer:
  • Machine installation
  • Large-scale production and manufacturing setup
Case Study
Transmission test room installation

Beck & Pollitzer worked on a project in Turkey involving the installation of helicopter gearbox testing units.

What initially began as personnel support was soon fully taken over by Beck & Pollitzer. The team was chosen by the client for their exemplary discipline in risk management and successfully fulfilled all responsibilities.

The team was responsible for:

Unpacking and unloading equipment in the warehouse

Delivering and positioning components in the installation area according to the assembly sequence

Marking out the installation site based on approved layouts and equipment positioning plans

Assembling steel structures and completing machine connections with proper alignment and torque

During the project, the team utilized a 5-ton forklift and a 55-ton crane to complete the installation.


1400
Man-hours